PROBLEM LINK:
Practice
Contest: Division 1
Contest: Division 2
Contest: Division 3
Contest: Division 4
Author: notsoloud
Tester: yash_daga
Editorialist: iceknight1093
DIFFICULTY:
468
PREREQUISITES:
None
PROBLEM:
Can X assignments, each requiring Y minutes, be completed within Z days?
EXPLANATION:
We have X assignments that need Y minutes each.
In total, we’d need X\cdot Y minutes to finish them all.
In Z days, there are 24\cdot 60\cdot Z minutes (24 hours in a day, 60 minutes in an hour).
So, the answer is Yes
if X\cdot Y \leq 1440\cdot Z and No
otherwise.
TIME COMPLEXITY
\mathcal{O}(1) per testcase.
CODE
Editorialist's code (Python)
for _ in range(int(input())):
x, y, z = map(int, input().split())
print('Yes' if x*y <= 24*60*z else 'No')